General contracting for the KONPACK company in Konin

218028836 1411993355846110 7181246994089330641 n

News from the construction site for the KONPACK company, a production and warehouse building with an office and social part in Konin.

The course of works:
– we are finishing the bricklaying works of the fire walls of the hall structure
– we are going on with paving works related to profiling and stabilizing the internal roads and laying paving stones and profiling green areas
– works related to covering the details of the roof, are in progress
– aeration shutters and bases for fans roofing are mounted
– works related to the assembly of the hall’s cladding and stabilization of the ground inside the hall in case of prepare it for the proper floor, are in progress
– works related to the execution of an under-floor lightning protection net, are in progress

 – in the office building, plastering works and laying of central heating and water installations are in progress